Sanford School

  • New middle school addition and building remodel
  • Project consisted of three new classrooms and remodeling three existing
  • Added and modified the combination low pressure steam system and hot water heat HVAC piping.
  • Worked with the district to keep heating systems operations during school year. This was a two-summer phased project which required extensive planning and forethought ahead of time.
  • At the completion of the project the building was commission by a third party commissioning agent.
  • Prefabricated all carrier groups which allowed the general contractor to accelerate the schedule.